“The Lines Aren’t That Close” Is Not a Power-Line Plan

Why electrical exposure must be identified, escalated, controlled, and priced before the crane arrives

One of the most dangerous phrases in crane sales is also one of the most common: “There are power lines, but they are not that close.” The statement sounds reassuring, but it does not provide the information needed to evaluate the job.


Close to what? The setup location? The boom path? The load? The rigging? The counterweight? The support trucks? The assembly area? A crane operation uses space in ways that may not be obvious to the customer making the request.


Power-line exposure is a sales-facing issue because it can change the setup, equipment, schedule, utility coordination, personnel, controls, and price. It must be identified before the quote becomes a commitment.

By: Joe | Hook Risk Management

Power lines should never be treated as a detail the operator can sort out after mobilization.

The Customer Sees the Final Pick

Customers often focus on the load’s final destination. They may look at the rooftop unit, transformer pad, sign structure, or piece of equipment and conclude that the power lines are outside the immediate work area.


The crane company must consider the entire operation. The crane has to enter the site, travel, set up, assemble if necessary, swing, boom, hoist, and leave. The load and rigging may move through a different path than the crane. Counterweights, support trucks, and personnel may occupy additional areas.


Sales should ask for photographs, site plans, line locations, voltage information when available, and the proposed setup and load path. When the relationship is unclear, the job should be escalated before pricing is finalized.

Utility Coordination Is Part of the Scope

Power-line work may require utility contact, de-energization, grounding, relocation, insulation measures, dedicated spotters, barricades, alternate setup, revised sequencing, or other controls depending on the circumstances and applicable requirements.


Those controls take time and require responsibility. The quote should identify who is contacting the utility, who is confirming the line status, who is providing any required personnel or barriers, and what documentation or schedule dependencies apply.


The crane company should not rely on a customer’s statement that the lines will be handled unless the process and responsible party are clear. A promise that the utility “will be there that morning” is not the same as a completed coordination plan.

Electrical exposure is not controlled by optimism, familiarity, or the customer’s deadline. It is controlled by verified information and a defined plan.

Power Lines Change Equipment and Setup Decisions

An alternate setup location may increase radius and require a larger crane. A smaller crane may fit the site but create a less favorable boom path. A different configuration, boom length, or assembly area may be needed to maintain the required clearance and control the work.


The company may also need additional time for a site visit, pre-job meeting, utility coordination, barricading, dedicated spotters, or revised traffic control. Those needs should be included in the scope and price.


Quoting only the crane and operator ignores the cost of the controls that make the job possible. If the customer will not pay for the controls, the job has not become safer. It has become underfunded.

The Field Team Needs a Clear Stop Point

Conditions may differ when the crew arrives. The line may be closer than represented. The setup area may have moved. The utility may not have completed the promised work. Other contractors may be occupying the intended control zone.


The operator and field team must know that work will not begin until the required conditions are confirmed. The quote and pre-job communication should support that position, including the company’s right to stop, revise, or remobilize when the exposure is not controlled.


A field crew should not be expected to negotiate utility responsibilities while the customer is pressing to complete the lift. Those responsibilities should have been assigned before mobilization.


Power-line work may require utility contact, de-energization, grounding, relocation, insulation measures, dedicated spotters, barricades, alternate setup, revised sequencing, or other controls depending on the circumstances and applicable requirements.


Those controls take time and require responsibility. The quote should identify who is contacting the utility, who is confirming the line status, who is providing any required personnel or barriers, and what documentation or schedule dependencies apply.


The crane company should not rely on a customer’s statement that the lines will be handled unless the process and responsible party are clear. A promise that the utility “will be there that morning” is not the same as a completed coordination plan.

Power-line intake should confirm:
  • Whether overhead or nearby electrical lines are present anywhere in the crane, load, rigging, counterweight, assembly, or support-equipment work area.
  • Available line-location and voltage information and who supplied it.
  • Who is responsible for utility coordination, de-energization, grounding, relocation, barricades, and other required controls.
  • Whether the proposed setup, boom path, and load path can be evaluated from the information provided.
  • What additional time, personnel, equipment, site review, permits, or contingency must be included in the price.

Sales Should Escalate Uncertainty, Not Explain It Away

Salespeople sometimes feel pressure to keep the customer moving by minimizing a concern they cannot fully evaluate. Power lines are not an area for reassurance without facts.


The professional response is straightforward: “We need to review the line location, voltage, proposed setup, and utility-control responsibilities before finalizing the equipment and price.” That response protects the customer as much as the crane company.


The objective is not to make sales perform an electrical-hazard analysis. It is to make sure sales recognizes the trigger and involves qualified operations, safety, management, utility, or engineering resources as needed.

Three Controls for Power-Line Work

1. Make power-line questions mandatory.

Do not allow “yes/no” to be the end of the intake. Require location, voltage information when available, photographs or plans, proposed setup, and the responsible utility-contact party.


2. Establish automatic escalation.

Any unclear or potentially relevant power-line exposure should receive operational and safety review before the quote is issued.


3. Price the control plan.

Include the time and cost of site review, utility coordination, alternate equipment, spotters, barricades, traffic control, schedule contingency, and standby exposure.


Power-line work may require utility contact, de-energization, grounding, relocation, insulation measures, dedicated spotters, barricades, alternate setup, revised sequencing, or other controls depending on the circumInclude the time and cost of site review, utility coordination, alternate equipment, spotters, barricades, traffic control, schedule contingency, and standby exposure.stances and applicable requirements.


Those controls take time and require responsibility. The quote should identify who is contacting the utility, who is confirming the line status, who is providing any required personnel or barriers, and what documentation or schedule dependencies apply.


The crane company should not rely on a customer’s statement that the lines will be handled unless the process and responsible party are clear. A promise that the utility “will be there that morning” is not the same as a completed coordination plan.

A Plan Begins Before Dispatch

Power-line safety depends on what happens at the site, but the ability to control the exposure often depends on decisions made much earlier. The company needs time to obtain information, coordinate the utility, choose the setup, and explain the requirements to the customer.


When the first meaningful discussion occurs at the morning job briefing, the company may already be behind. The crane is mobilized, the customer’s schedule is running, and everyone feels pressure to make the existing plan work.


“The lines are not that close” is not a plan because it does not define distance, responsibility, or control. A professional crane company replaces that phrase with verified information, documented roles, and a price that supports the controls required.